341844140
|
0111500
|
2016-10-14
|
405 BRIDGEPORT AVE., SHELTON, CT, 06484
|
|
Inspection Type |
Planned
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2016-10-14
|
Emphasis |
L: FALL, P: FALL
|
Case Closed |
2017-11-15
|
Violation Items
Citation ID |
01001A |
Citaton Type |
Serious |
Standard Cited |
19260501 B01 |
Issuance Date |
2016-11-09 |
Abatement Due Date |
2016-11-22 |
Current Penalty |
2620.0 |
Initial Penalty |
3741.0 |
Final Order |
2016-12-07 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.501(b)(1): Each employee on a walking/working surface with an unprotected side or edge which was 6 feet (1.8 m) or more above a lower level was not protected from falling by the use of guardrail systems, safety net systems, or personal fall arrest systems. Worksite: The employer did not ensure that the employees who were required to work from the edge of the roof at a height above six feet were protected from falling by the use of guardrail systems, safety net systems, or personal fall arrest systems. |
|
Citation ID |
01001B |
Citaton Type |
Serious |
Standard Cited |
19260503 A01 |
Issuance Date |
2016-11-09 |
Abatement Due Date |
2016-12-07 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2016-12-07 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.503(a)(1): The employer did not provide a training program for each employee potentially exposed to fall hazards to enable each employee to recognize the hazards of falling and the procedures to be followed in order to minimize these hazards. Worksite: The employer did not ensure that the employees who were required to work from the roof of the building under construction at a height above six feet were trained in fall hazards and the procedures to be followed to minimize such hazards. |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19260451 E01 |
Issuance Date |
2016-11-09 |
Abatement Due Date |
2016-11-22 |
Current Penalty |
1495.0 |
Initial Penalty |
2138.0 |
Final Order |
2016-12-07 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were not allowed to use as a means of access. Worksite: The employer did not provide a safe means of access for employees who were required to access the second level platform of the metal frame scaffold. |
|
Citation ID |
01003 |
Citaton Type |
Serious |
Standard Cited |
19260451 E08 |
Issuance Date |
2016-11-09 |
Abatement Due Date |
2016-11-22 |
Current Penalty |
2245.0 |
Initial Penalty |
3207.0 |
Final Order |
2016-12-07 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(e)(8): Direct access to or from another surface was used when the scaffold was more than 14 inches (36 cm) horizontally and/or 24 inches (61 cm) vertically from the other surface. Worksite: The employer did not provide a means of access for employees who were required to gain access to the roof of the building from the scaffold platform that was located 5 feet 6 inches below the roof. |
|
Citation ID |
01004A |
Citaton Type |
Serious |
Standard Cited |
19260451 F07 |
Issuance Date |
2016-11-09 |
Abatement Due Date |
2016-12-07 |
Current Penalty |
1870.0 |
Initial Penalty |
2672.0 |
Final Order |
2016-12-07 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration:; Such activities were not performed only by experienced and trained employees selected for such work by the competent person. Worksite: The employer did not ensure that the metal frame scaffold that employees were required to use as a means of access to the roof of the building under construction was erected under the supervision of a person competent in scaffold erection. |
|
Citation ID |
01004B |
Citaton Type |
Serious |
Standard Cited |
19260454 A01 |
Issuance Date |
2016-11-09 |
Abatement Due Date |
2016-12-07 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2016-12-07 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.454(a)(1): The employer failed to have each employee who performs work while on a scaffold trained regarding the nature of any electrical hazards, fall hazards and falling object hazards in the work area. Worksite: The employer did not ensure that employees who were required to use metal frame scaffolding as a means of access to the roof of the building under construction were trained to recognize the hazards associated with the type of scaffold being used. |
|
Citation ID |
01005 |
Citaton Type |
Serious |
Standard Cited |
19260451 G01 VII |
Issuance Date |
2016-11-09 |
Abatement Due Date |
2016-11-22 |
Current Penalty |
1870.0 |
Initial Penalty |
2672.0 |
Final Order |
2016-12-07 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(g)(1)(vii): Each employee on a scaffold, not otherwise specified in paragraphs (g)(1)(i) through (g)(1)(vi) of this section, more than 10 feet (3.1 m) above lower level was not protected from falls by the use of personal fall arrest systems or guardrail systems meeting the requirements of paragraph (g)(4) of this section. Worksite: The employer did not ensure that the employees who were required to use the metal frame scaffold as a means of access to the roof of the building under construction were protected from fall hazards by the use of guardrails or personal fall arrest systems. |
|
Citation ID |
02001 |
Citaton Type |
Other |
Standard Cited |
19100178 L04 III |
Issuance Date |
2016-11-09 |
Abatement Due Date |
2016-12-07 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2016-12-07 |
Nr Instances |
1 |
Nr Exposed |
1 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.178(l)(4)(iii): An evaluation of each powered industrial truck operator's performance was not being conducted at least once every three years. Worksite: The employer did not ensure that the performance of the employee who was required to operate the all-terrain forklift was evaluated at least once every three years. |
|
|
337425615
|
0111500
|
2012-11-15
|
121 CONNECTICUT AVE, NORWALK, CT, 06854
|
|
Inspection Type |
Planned
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2012-11-15
|
Emphasis |
L: FALL, N: CTARGET
|
Case Closed |
2013-02-01
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19261053 B13 |
Issuance Date |
2012-12-17 |
Abatement Due Date |
2012-12-26 |
Current Penalty |
1120.0 |
Initial Penalty |
1600.0 |
Final Order |
2013-01-29 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.1053(b)(13): The top or step of a stepladder was used as a step: Worksite: Employees who were performing masonry work in the rear of the building were standing on the top step of an eight foot step ladder. |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19261053 B16 |
Issuance Date |
2012-12-17 |
Current Penalty |
1120.0 |
Initial Penalty |
1600.0 |
Final Order |
2013-01-29 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.1053(b)(16): Portable ladders with structural defects, such as, but not limited to, broken or missing rungs, cleats, or steps, broken or split rails, corroded components, or other faulty or defective components, were not either immediately marked in a manner that readily identifies them as defective, or tagged with "Do Not Use" or similar language, and were not withdrawn from service until repaired or replaced. Worksite: The employer did not ensure that Werner step ladder, which had a broken spreader bar, was removed from service until repaired or replaced. |
|
|
314715228
|
0111500
|
2010-09-09
|
1407 MELVILLE AVE., FAIRFIELD, CT, 06825
|
|
Inspection Type |
Complaint
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2010-09-09
|
Case Closed |
2011-02-15
|
Related Activity
Type |
Complaint |
Activity Nr |
206678351 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260102 A01 |
Issuance Date |
2010-11-19 |
Abatement Due Date |
2010-11-24 |
Current Penalty |
1000.0 |
Initial Penalty |
1000.0 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
05 |
|
|
313359309
|
0111500
|
2009-06-24
|
695 PARK AVENUE, BRIDGEPORT, CT, 06604
|
|
Inspection Type |
Prog Related
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2009-06-24
|
Emphasis |
S: RESIDENTIAL CONSTR
|
Case Closed |
2010-10-13
|
Violation Items
Citation ID |
01001A |
Citaton Type |
Serious |
Standard Cited |
19100134 C04 |
Issuance Date |
2009-11-05 |
Abatement Due Date |
2009-12-03 |
Current Penalty |
600.0 |
Initial Penalty |
600.0 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
01 |
|
Citation ID |
01001B |
Citaton Type |
Serious |
Standard Cited |
19100134 F01 |
Issuance Date |
2009-11-05 |
Abatement Due Date |
2009-12-03 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
01 |
|
Citation ID |
01002A |
Citaton Type |
Serious |
Standard Cited |
19100134 G01 IA |
Issuance Date |
2009-11-05 |
Abatement Due Date |
2009-12-03 |
Current Penalty |
600.0 |
Initial Penalty |
600.0 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
01 |
|
Citation ID |
01002B |
Citaton Type |
Serious |
Standard Cited |
19100134 K03 |
Issuance Date |
2009-11-05 |
Abatement Due Date |
2009-12-03 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
01 |
|
Citation ID |
01003A |
Citaton Type |
Serious |
Standard Cited |
19101200 E01 |
Issuance Date |
2009-11-05 |
Abatement Due Date |
2009-12-03 |
Current Penalty |
600.0 |
Initial Penalty |
600.0 |
Nr Instances |
1 |
Nr Exposed |
3 |
Gravity |
01 |
|
Citation ID |
01003B |
Citaton Type |
Serious |
Standard Cited |
19101200 G08 |
Issuance Date |
2009-11-05 |
Abatement Due Date |
2009-12-03 |
Nr Instances |
1 |
Nr Exposed |
3 |
Gravity |
01 |
|
|
308625649
|
0111500
|
2005-05-17
|
5065 MAIN STREET - FILENE'S & TRUMBULL MALL, TRUMBULL, CT, 06611
|
|
Inspection Type |
Planned
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2005-05-25
|
Emphasis |
L: FALL
|
Case Closed |
2005-06-29
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Repeat |
Standard Cited |
19260453 B02 V |
Issuance Date |
2005-06-06 |
Abatement Due Date |
2005-06-09 |
Current Penalty |
2600.0 |
Initial Penalty |
4000.0 |
Nr Instances |
2 |
Nr Exposed |
3 |
Gravity |
10 |
|
|
123155558
|
0111500
|
2004-09-16
|
80 TEMPLE STREET, NEW HAVEN, CT, 06510
|
|
Inspection Type |
Prog Related
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2004-09-21
|
Case Closed |
2005-01-13
|
Related Activity
Type |
Inspection |
Activity Nr |
123155525 |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260451 G01 VI |
Issuance Date |
2004-10-08 |
Abatement Due Date |
2004-10-14 |
Current Penalty |
1000.0 |
Initial Penalty |
1000.0 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
03 |
|
Citation ID |
02001 |
Citaton Type |
Repeat |
Standard Cited |
19260501 B04 I |
Issuance Date |
2004-10-08 |
Abatement Due Date |
2004-10-14 |
Current Penalty |
2000.0 |
Initial Penalty |
2000.0 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
03 |
|
|
123158545
|
0111500
|
2004-09-03
|
1042 BROAD STREET, BRIDGEPORT, CT, 06604
|
|
Inspection Type |
Prog Related
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2004-09-07
|
Emphasis |
L: FALL
|
Case Closed |
2005-06-01
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260451 G02 |
Issuance Date |
2004-11-22 |
Abatement Due Date |
2004-11-30 |
Current Penalty |
2000.0 |
Initial Penalty |
2000.0 |
Nr Instances |
2 |
Nr Exposed |
3 |
Gravity |
10 |
|
Citation ID |
01002A |
Citaton Type |
Serious |
Standard Cited |
19260453 B02 IV |
Issuance Date |
2004-11-22 |
Abatement Due Date |
2004-11-26 |
Current Penalty |
1000.0 |
Initial Penalty |
1000.0 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
03 |
|
Citation ID |
01002B |
Citaton Type |
Serious |
Standard Cited |
19260453 B02 V |
Issuance Date |
2004-11-22 |
Abatement Due Date |
2004-11-26 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
03 |
|
Citation ID |
01003A |
Citaton Type |
Serious |
Standard Cited |
19261053 B09 |
Issuance Date |
2004-11-22 |
Abatement Due Date |
2004-11-26 |
Current Penalty |
1400.0 |
Initial Penalty |
1400.0 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
05 |
|
Citation ID |
01003B |
Citaton Type |
Serious |
Standard Cited |
19261053 B15 |
Issuance Date |
2004-11-22 |
Abatement Due Date |
2004-11-26 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
05 |
|
Citation ID |
01003C |
Citaton Type |
Serious |
Standard Cited |
19261053 B16 |
Issuance Date |
2004-11-22 |
Abatement Due Date |
2004-11-26 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
05 |
|
|
305820912
|
0112000
|
2003-02-13
|
9 JUDD AVENUE, KENT, CT, 06757
|
|
Inspection Type |
Prog Related
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2003-02-13
|
Emphasis |
L: EISA, S: CONSTRUCTION
|
Case Closed |
2003-05-02
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260025 A |
Issuance Date |
2003-03-20 |
Abatement Due Date |
2003-03-24 |
Current Penalty |
400.0 |
Initial Penalty |
800.0 |
Nr Instances |
1 |
Nr Exposed |
6 |
Gravity |
02 |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19260405 A02 III |
Issuance Date |
2003-03-20 |
Abatement Due Date |
2003-03-24 |
Current Penalty |
500.0 |
Initial Penalty |
1000.0 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
03 |
|
Citation ID |
01003 |
Citaton Type |
Serious |
Standard Cited |
19260501 B01 |
Issuance Date |
2003-03-20 |
Abatement Due Date |
2003-03-25 |
Current Penalty |
500.0 |
Initial Penalty |
1000.0 |
Nr Instances |
1 |
Nr Exposed |
3 |
Gravity |
03 |
|
|
123286825
|
0111500
|
2002-09-17
|
NORTH AVENUE AT HOUSATONIC AVENUE, BRIDGEPORT, CT, 06606
|
|
Inspection Type |
Prog Related
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2002-09-17
|
Emphasis |
L: EISA, L: FALL, L: FORKLIFT, S: CONSTRUCTION
|
Case Closed |
2002-10-09
|
Violation Items
Citation ID |
01001A |
Citaton Type |
Serious |
Standard Cited |
19260102 A01 |
Issuance Date |
2002-09-24 |
Abatement Due Date |
2002-09-28 |
Current Penalty |
375.0 |
Initial Penalty |
750.0 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
04 |
|
Citation ID |
01001B |
Citaton Type |
Serious |
Standard Cited |
19260096 |
Issuance Date |
2002-09-24 |
Abatement Due Date |
2002-09-28 |
Nr Instances |
1 |
Nr Exposed |
3 |
Gravity |
04 |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19260602 C01 VI |
Issuance Date |
2002-09-24 |
Abatement Due Date |
2002-09-28 |
Current Penalty |
225.0 |
Initial Penalty |
450.0 |
Nr Instances |
1 |
Nr Exposed |
7 |
Gravity |
01 |
|
Citation ID |
02001 |
Citaton Type |
Other |
Standard Cited |
19260451 E01 |
Issuance Date |
2002-09-24 |
Abatement Due Date |
2002-09-27 |
Nr Instances |
1 |
Nr Exposed |
7 |
Gravity |
01 |
|
|